2003 – Fraunhofer Society in Dresden, Building for the Institute

Project

Extension buildings for the Fraunhofer Society 
Dresden, Winterbergstrasse
  
Construction period: 2001 – 2003


Client

Fraunhofer Society
Hansastrasse 27
80686 Munich


Activities

  • Investigation and expertise of the ground
  • Advices for foundation
  • Planning of measures for groundwater lowering
  • Modelling of groundwater contour lines during lowering including the simulation of transports of noxious substances resulting from soil contaminations in the downstream flow
  • Application documents for the water-related application procedure

Period of activities: 2001 – 2003