2006 – New Railway Line Nuremberg – Ingolstadt, Lot South

Project

New railway line Nuremberg – Ingolstadt, Lot South
High speed railway line
 
Construction period: 1998 – 2006

  
Client

DB ProjektBau GmbH
Branch South
Project centre Nuremberg 1
Oedenberger Strasse 55
90491 Nuremberg


Activities

  • Protection of slopes in cuttings in difficult soil and groundwater relations
  • Realisation of improved soil models in consideration of difficult soil and groundwater relations
  • Feasibility studies for slope protections with dowels and supporting plates
  • Feasibility study and determination of planning foundations for a tunnel in cut-and-cover method
  • Feasibility study for the proof of effenciency of track protection with geogrid constructions under embankments in railway line sections endangered by karst and depression

Period of activities: 1998 – 2006

< Back to references