Project

New railway line Ebensfeld – Erfurt
High speed railway line

Authorised EBA expert for geotechnics for the tender package
Lichtenfels (km 9,090 to km 15,144)

Construction period: since 2009

  
Client

DB ProjektBau GmbH
Regionalbereich Südost
Großprojekte VDE 8
Kurt-Schumacher-Straße 1
99084 Erfurt

  
Activities (still in progress)

  • Checking the design of earthworks including drainages as well as road and landfill construction according to German Standard VV Bau and interim acceptance 
  • Fields of activity for inspections:
    Earthworks for tunnel precuts, embankments and cuttings,
    slope stabilisation with dowels and surface filters,
    support plate made of soil stabilised with binding material,
    bleeder well,
    contiguous bored pile walls

Period of activities: 2009 – 2014

< Back to references